Updated 1.0.0 release criteria; draft 1.0.0 release plan
Alexandre Julliard
julliard at winehq.org
Sat Mar 15 16:32:17 CDT 2008
Michael Stefaniuc <mstefani at redhat.com> writes:
> Alexandre Julliard wrote:
>> We need a code freeze and stabilization period before the release. My
>> thinking is that we should have a 1.0rc1 release, probably sometime in
>> May, and from that point on only accept small obvious fixes. Then we'd
> What about small janitorial patches?
Obvious low risk patches could go in, but I don't see much need to put
in janitorial patches during the rc phase, they can just as well wait
until 1.0 is out.
--