Alexandre Julliard
julliard at winehq.org
Sun May 9 04:43:41 CDT 2010
Tom Wickline <twickline at gmail.com> writes:
> I thought the code freeze, RC cycle would be more like three months not
> three releases, e.g six weeks.
> But I'm 100% sure AJ knows best. :)
Nobody said it can't be three months. It will last as long as good fixes
keep pouring in. In practice after 1-2 months we usually run out of bugs
that can be reasonably fixed; at that point it wouldn't make sense to
hold the release for another month to get 3 extra fixes.
And like last time, I'm planning to make rc releases on a weekly
schedule, so we should get plenty of them.
--
Alexandre Julliard
julliard at winehq.org