7.0 release plans

Alexandre Julliard julliard at winehq.org
Sat Nov 20 05:47:53 CST 2021


Folks,

With the end of the year approaching, it's time to start thinking about
the code freeze towards Wine 7.0.

My plan is to make one more development release (6.23) two weeks from
now, and start the code freeze one week after that, with a 7.0-rc1
release on December 10. We'll then have the usual weekly rc releases,
until the final 7.0 sometime in the second half of January.

This means that if you have things that you'd like to see in 7.0, you
still have 3 weeks to get them upstream...

-- 
Alexandre Julliard
julliard at winehq.org